The Mill Test Certificate is the single document a steel buyer checks first, and the difference between EN 10204 type 3.1 and type 3.2 is the difference between a mill declaration and an independently witnessed inspection. Most buyers do not know which one their purchase order actually requires until the cargo is at the port and the inspection agency asks for it. This guide explains what each section of the certificate means, what to verify on receipt, and the four clauses that most often cause a shipment to be held.
EN 10204 classifies inspection documents into three types. The distinction is not academic — it determines who is standing behind the numbers when a buyer's engineer asks whether the material in front of them is what was ordered.
| Certificate type | What it is | Who takes responsibility | When it is used |
|---|---|---|---|
| Type 2.1 / 2.2 | Test report based on the works test results | Mill self-declaration, no third party | Routine commercial orders, low risk |
| Type 3.1 | Inspection certificate, independently verified by a third-party inspection body | Body audits the mill's certificate against its own witness records | Most export contracts, oil & gas, structural |
| Type 3.2 | Inspection certificate, third party witnesses and takes responsibility for the test | Body present at testing, signs for the results directly | Critical service, sour/offshore, project-specified |
The practical question for a buyer is simple: what does your purchase specification and your end client require? Written as "EN 10204 3.1" and written as "mill certificate" are very different instructions to a mill, and the difference in cost and lead time is real. If the specification does not say, ask your client before the mill does — a certificate type change partway through production costs more than a week.
A complete inspection certificate has more sections than most buyers ever read. These are the ones that carry real commercial weight:
| Section | What it contains | Why it matters |
|---|---|---|
| Heat number | Must match the marking on the material and the packing list | The link between certificate and physical steel |
| Chemical analysis | C, Si, Mn, P, S, plus alloy elements if any | Grade identity — this is where a substituted grade gets caught |
| Mechanical properties | Yield strength, tensile strength, elongation, Charpy values where applicable | Confirms the grade actually meets the standard |
| Dimensions and weight | Thickness, width, length, piece weight, total weight | Basis for your weight-based payment and for customs |
| Surface condition / coating | Edge condition, passivation, oiled or bare, coating weight for coated material | The four clauses that most often hold up a shipment |
Across the shipments we handle, the same four issues recur, and in every case they are visible on the certificate before the cargo sails if somebody checks:
All four are cheaper to fix before loading than after arrival. This is why we issue the certificate for review before shipment on request — the inspection is more useful before the cargo leaves than after.
When the container is opened, before the steel is put into production:
Photographs taken at discharge are also your evidence for any subsequent claim, which is why we shoot loading photographs and video as standard and can make them available before loading completes.
For how the certificate type affects what a pipe order needs, see API 5L versus ASTM A106. For the standard numbering differences between mills that quote ASTM, EN and JIS, see our standards cross-reference.
Both are inspection certificates under EN 10204. The difference is who takes responsibility for the test results. In a 3.1 certificate, an accredited third-party inspection body reviews the mill's own test results and its own witnessing records, and issues the certificate against the mill's declaration. In a 3.2 certificate, the inspection body witnesses the tests itself and takes direct responsibility for the reported values. For most structural and general industrial shipments a 3.1 certificate is entirely normal. For sour service, offshore and API 5L PSL2 pipeline projects, 3.2 is normally mandatory because the certificate is what carries the impact test results.
A mill-issued document is a type 2.1 or 2.2 document — a test report based on the works test results. It is perfectly valid for many contracts and buyers accept it. But it is a declaration by the party that sold you the material, with no independent check. If your purchase specification calls for EN 10204 3.1 or 3.2, a type 2.1 document does not satisfy it, and the inspection agency will say so at the port rather than at the mill. Specify the certificate type on the order, and specify the inspection body by name where you want 3.2.
In our experience the recurring ones are: coating weight on coated material not meeting the specified minimum; edge condition showing damage or poor shearing; passivation or oiling missing when the material is going into a paint line or food-contact application; and the weight per piece not reconciling with the declared total weight for customs valuation. All four are visible on the certificate before shipment if someone on the buyer's side reads it, and all four are far cheaper to fix before loading than after arrival.
Yes, and this is worth being explicit about. Certificates issued in Chinese or with a mill's own bilingual format are accepted by most inspection agencies after translation, but the translation step adds days and creates a document that differs from the original. We issue certificates in English with the Chinese original retained on file, and we can pre-agree the format with your inspection body before production rather than after the vessel has sailed.
One certificate per heat, not per coil. A coil shipment normally involves several heats, so expect several certificates, cross-referenced to a packing list that shows which heat maps to which coil. The important thing is that every coil in the shipment is covered by a certificate and that the heat number on the physical marking matches. We issue a consolidated index so the mapping is done for you rather than left to whoever opens the container.
For hot-dip galvanized and pre-painted coil it should. The coating weight must appear as an actual measured value, not just the nominal grade, because the standard permits a tolerance band and the mill certifies what was actually applied. If your specification states a minimum total coating weight in g/m², the certificate value is what is checked. See our guide on G60 versus G90 coating weights for what the numbers mean.
Send grade, thickness, width, coating and quantity. We confirm mill availability and return a proforma with the applicable standard and delivery window — normally within one business day.